0514
The Deputy Chief Fire Officer updated the Authority on the implementation measures taken in support of the Resource Review.
Members' attention was drawn to an error in paragraph 8, the reinvestment figure should have read circa £180,000.
Members discussed an email they had received the night before the meeting from the Fire Brigades Union, in particular with reference to the use of the 4x4 vehicles. There were concerns that the email had not been sent to senior officers and that these were issues the FBU should have raised with officers in the first instance.
Members were reminded that it was very clear in the resource review that the 4x4 vehicles were to be used to transport people to an incident and anyone with a driving licence could drive them. They were not to replace fire engines, nor to be equipped with equipment and were already proving a valuable asset to the Service by improving response arrangements.
Members noted that the full reallocation of resources should be completed in 2025 and be fully embedded by the end of 2025. Early indications showed the outcomes of the Resource Review were having a positive effect on crewing levels at wholetime locations and the Service should see an upturn in On-Call availability in the near future.
[Cllr D Chambers and Cllr A Ditta left the meeting at 11.41am].
RESOLVED that Members note progress to date regarding measures taken to implement the outcome of the Resource Review, in particular:
i) Removal of the proposed fire engines (listed below);
ii) The wholetime watch position at Hereford, Worcester and Wyre Forest;
iii) Operational use of the new 4x4 vehicles;
iv) The updated capital financing costs; and
v) Implementation of the new model for daytime support crewing at Leominster and Bromyard.