0248
The Assistant Chief Fire Officer - Director of Protection and Assets provided Members with an update on the current property programme.
Members had previously been informed of the inflationary pressures being seen across the building sector. Taking this into account the Treasurer is building in contingency funds in anticipation of the current capital build programme. Members will be updated as the projects develop, with particular regard to the largest projects, notably Redditch and Hereford Fire Station builds.
With regard to the Hereford fire station rebuild, Members were informed that only one suitable location had been identified for use as a temporary fire station during the rebuild. In order to ensure those premises were available when required, it would be necessary for the Authority to enter into a lease of the premises now, even though the overall costs of the scheme had not yet been finally approved. The temporary location would also require planning permission for change of use. There was therefore an element of risk involved by entering into a lease at this stage. Members were given details of the proposed lease and following discussion, Members agreed for Officers to proceed with the lease.
At the Policy and Resources Committee meeting in September it was reported that a full planning application for the North Herefordshire Strategic Training Facility had been submitted to Herefordshire Council on 20 December 2022, this had now been approved.
Members noted that a tender process via a construction procurement framework to identify a suitable contractor to build the training facility had closed and contractor interviews were progressing.
Although there was concern from Members in relation to the additional costs of contamination surveys for the disposal of the Kidderminster fire station site, Members were assured that investing money in surveys would strengthen the resale.
A Member queried the capacity for project management of the new builds. The Chief Fire Officer assured Members that as well as our in-house Property and Estates Manager, project management was also undertaken by the office of the PCC on our behalf.
RESOLVED that:
1) The property update and progress of the capital build programme and property maintenance is noted at:
i) Broadway Fire Station;
ii) Redditch Fire Station;
iii) Hereford Fire Station;
iv) North Herefordshire Strategic Training Facility;
v) Relocation of Training Centre to Wyre Forest Fire Station; and
vi) Planned and reactive property maintenance.
2) Officers be authorised to enter into a lease of premises at Hereford for use as a temporary fire station in order to secure the location pending final approval of the new build scheme by the Authority.